|
|
|
Process Problems
- Lincoln Treatment Plant
The District faced 4 difficult problems during the early years
of operations:
a. Biosolids Disposal
b. Composting Odors
c. Excessive weight on RBC Shafts
d. CSO discharges
The District lime stabilized and land applied biosolids from
1982 to 1988 on silage corn fields of local dairy farmers.
Permitting sites was difficult due to public opposition and
incorporation of the biosolids into the soil was necessary for
odor control at the sites. The diary farmers were slowly being
squeezed out of business due to economic conditions and no other
nearby sites were available to allow incorporation of biosolids.
The Superintendent developed a windrow composting program
utilizing the biosolids storage shed for part of the year in
1987. About half of all the biosolids produced were composted
and half land applied through 1988. All biosolids produced were
composted when the last dairy farm closed in 1989.
RBC Shaft weight became excessive, threatening premature shaft
failure whenever wastewater temperatures dropped below 10
degrees Celsius. This condition generally occurred from November
through May and all attempts to control shaft weights were
unsuccessful. Numerous control measures were tried including air
purging, in-line chlorination, isolation and starvation, and
chemical stripping but all were unsatisfactory because they
either did not remove the excess biomass or when they did,
effluent quality suffered.
The Superintendent found the solution to the RBC shaft weight
problem while attending the January 1994 NEWEA Conference when a
paper presentation by Kenneth E. Neu discussed upgrading RBC
systems to achieve higher quality effluent thru solids
recirculation. If the treatment plant could recirculate
secondary solids (and in effect run an activated sludge system
in concert with the RBC’s) it would reduce shaft weights and
provide better treatment. Unfortunately there was no primary
clarification at that time so the idea was put on hold.
Despite the best efforts of plant operators, by 1997 the
District was faced with a continuing CSO problem and it became
clear that an upgrade to the plant was needed to eliminate the
CSOs. An opportunity presented itself to eliminate several
problems with one upgrade. In 1999 the upgrade was constructed
to include primary clarification and secondary solids
recirculation. The district direct purchased and installed two
return pumps and portable blowers for conversion of the windrow
composting to aerated static pile. The upgrade eliminated
composting odor problems, eliminated the CSO and eliminated the
excessive shaft weight problem.
The ability to re-circulate secondary solids improved treatment
and reduced power consumption. The average percent removal for
the period July thru October 2000 for BOD was 96.6% compared to
89.9 % for the same period in 1999. TSS average percent removal
was 95% compared to 89% for the same period in 1999. Energy
consumption has dropped because air required to turn the RBC’s
is less when biomass load on the shaft is less and because the
need for a 15 horsepower mixer in the blended sludge tank was
eliminated. Secondary solids are now co-thickened in the primary
tanks.
The Lincoln facility was the first and only RBC plant in the
state of Maine to re-circulate secondary solids.
|